On year 2013
- Implementation of the installation of steam, heat, nitrogen, vacuum, industrial process water, cooling, compressed air, vulcanizing, pressure filters, ventilation tunnel at the Pirelli factory in Settimo Torinese.
- Implementation of the installation of air conditioning, heat, fire prevention at the New Tower Intesa San Paolo of Turin.
On year 2012
- Implementation of the installation of central heating, refrigeration, fire alarm control panels, steam plant, distribution, re-heating, heat distribution and retention at the New Hospital of Lucca for New Busi.
On year 2011
- Execution of the construction works of niches to n. 514 columbarium at the cemetery Marsala city.
On year 2010
- Execution of construction and assembly work in turnkey (including testing and mechanical completion) piping from Dn 20 to Dn 500 and carpentry varies from plant to Palermo Constr. 6177 "Scarabeo 8" Fincantieri S.p.A. / Saipem.
On year 2009
- Implementation of the prefabrication of n. 980 tubes marcapezzo from Dn 20 to Dn 500 at Ns. establishment of Gela Constr. 6177 "Scarabeo 8" Fincantieri S.p.A. / Saipem.
- Implementation of the installation on site turnkey n. 980 tubes marcapezzo from Dn 20 to Dn 500 at plant in Palermo for Constr. 6177 "Scarabeo 8" Fincantieri S.p.A. / Saipem.
On year 2008
- Implementation of the prefabrication and assembling steel structures, cutlery at the tank of St. Rosalia (RG) for Garboli SpA (group Pizzarotti SpA).
On year 2007
- Implementation of the extension and maintenance of gas distribution networks, the derivations of users and of the risers at the UOT Mass, Enel Rete Gas SpA.
- Implementation of the shoring and demolition of unsafe buildings themselves, Vanelle Street in the town of Naro (AG).
On year 2006
- Implementation of the extension and maintenance of gas distribution networks, the derivations of users and of the risers at the UOT Mass, for CPL Concordia Soc.
- Implementation of public lighting, laying of water supply, pipeline, sewer and drain white water for the town of Ragusa Ibla.
On year 2005
- Implementation of the extension and maintenance of gas distribution networks, the derivations of users and of the risers at the UOT Mass, for Romana Costruzioni SRL.
On year 2004
- Execution of the exhaust Sakalin and Nigeria at the workshops VGF for Nuovo Pignone SpA.
- Execution of the total adjustment of all technological systems, at the Ramada Hotel in Giardini Naxos (ME).
On year 2003
- Execution of the piping, carpentry and welding related forms for the platform, at Cosm area of Nuovo Pignone Mass.
- Realization of laying, welding district heating networks from dn 50 to dn 300, near the city of Florence.
On year 2002
- Execution of the Hi-Fog at Fincantieri SpA (GE) of the ship, Costa Cruises 'Costa Fortuna'.
- Inch pipeline running 00:48 at Caprarico (MT).
- Realization of the exhaust white water, sewage and water mains, at Genoa Nervi.
On year 2001
- Execution of piping work, carpentry and welding on at CERN, Geneva (Switzerland).
- Execution of piping work, carpentry and welding on at CERN, Geneva (Switzerland).
- Realization gas network extension and ordinary and extraordinary maintenance of utilities and risers, in the province of Siena.
On year 2000
- Running the rolling plant at Ilva steelworks (GE).
- Execution of piping work, carpentry and welding related, at Burgo paper mill Verzuolo (CN).
- Making use of gas leads to condominiums, villas and houses in the center of Turin.
On year 1999
- Execution of the mock-vac and press-fitting at Fincantieri SpA, Marghera (VE) and the Hi-Fog at Fincantieri SpA (GE) of Walt Disney and Minoan Lines ship "Knossos Palace".
- Prefabrication of carpentry, piping and welding on skid for Nuovo Pignone destination Nigeria.